MS Project Exercises
Exercise 13.32
Using the following data, enter the various tasks and create a Gantt chart using MS Project. Assign the individuals responsible for each activity and once you have completed the network, update it with the percentage complete tool. What does the MS Project output file look like?
Activity |
Duration |
Predecessors |
Resource |
% Complete |
---|---|---|---|---|
A. Research product |
6 |
— |
Tom Allen |
100 |
B. Interview customers |
4 |
A |
Liz Watts |
75 |
C. Design survey |
5 |
A |
Rich Watkins |
50 |
D. Collect data |
4 |
B, C |
Gary Sims |
0 |
Exercise 13.33
Now, suppose we assign costs to each of the resources in the following amounts:
Resource |
Cost |
---|---|
Tom Allen |
$50/hour |
Liz Watts |
$55/hour |
Rich Watkins |
$18/hour |
Gary Sims |
$12.50/hour |
Create the resource ...