MS Project Exercises

Exercise 13.32

Using the following data, enter the various tasks and create a Gantt chart using MS Project. Assign the individuals responsible for each activity and once you have completed the network, update it with the percentage complete tool. What does the MS Project output file look like?

Activity

Duration

Predecessors

Resource

% Complete

A. Research product

6

Tom Allen

100

B. Interview customers

4

A

Liz Watts

75

C. Design survey

5

A

Rich Watkins

50

D. Collect data

4

B, C

Gary Sims

0

Exercise 13.33

Now, suppose we assign costs to each of the resources in the following amounts:

Resource

Cost

Tom Allen

$50/hour

Liz Watts

$55/hour

Rich Watkins

$18/hour

Gary Sims

$12.50/hour

Create the resource ...