Summary
10.1 Apply lag relationships to project activities. Examples of developing network logic include determining how precedence relationships apply to each project activity. That is, do activities follow one another in a common manner in which the predecessor’s early finish becomes the successor activity’s early start, or are other relationships specified? Among these alternative relationships, referred to as lag relationships, are Finish to Start, Finish to Finish, Start to Start, and Start to Finish.
10.2 Construct and comprehend Gantt charts. An alternative method for developing the project network other than the use of PERT diagrams is Gantt charts. Gantt charts offer an important advantage over the early PERT diagrams in that they link ...