MS Project Exercises
Please note that a step-by-step primer on using MS Project 2016 to create project schedules is available in Appendix B. For those considering the following exercises, it would first be helpful to refer to Appendix B for tips on getting started.
Exercise 9.27
Consider the following information that you have compiled regarding the steps needed to complete a project. You have identified all relevant steps and have made some determinations regarding predecessor/successor relationships. Using MS Project, develop a simple network diagram for this project, showing the links among the project activities.
Activity |
Predecessors |
---|---|
A – Survey site |
— |
B – Install sewer and storm drainage |
A |
C – Install gas and electric power lines ... |
Get Project Management: Achieving Competitive Advantage, Fifth Edition now with the O’Reilly learning platform.
O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.