Because the network diagram can be a long and detailed map of the project, you probably don't want to enter it into a computer on the first draft. One of the best methods of building and implementing the network diagram is on a whiteboard utilizing sticky notes. A project manager, along with the project team, should begin by defining the origin work unit on a sticky note and then defining the project deliverables on another sticky note. On the left of the whiteboard, place the origin task, and on the right, place the deliverables. Now the project manager and the project team can use the activity list to identify the relationships between the units of work.
You and the team will continue to create the PND by ...