34 • Practical Project Management for Building and Construction
installation of machinery, or integrated testing. e process also applies to
how knowledge areas are managed, such as
• WHAT permission or approval from the authorities is needed?
HOW is this obtained? WHEN is it necessary to apply and WHO
should do it?
• WHAT qualities should be controlled? HOW and WHEN is this
done and by WHOM?
• For WHAT area should a risk analysis be developed? HOW should
this be accomplished (method of identication, analysis, etc.)? WHO
should participate and WHO ensures the implementation of planned
measures to reduce the threats?
More about the areas ...