176 • Practical Project Management for Building and Construction
• Add the task’s duration, which will yield the “earliest activity-nish”
of activity j (EF
j
).
• ES
j
+ weighted average duration = EF
j
.
For multiple relationships, the ES of the subsequent activity is the latest
EF. When lag (delay) and lead (overlap) are taken into account,
ES
j
= EF
i
+ lag – lead
where ES
j
stands for early start activity j and EF
i
is the earliest nish of a
premature activity.
6.7.4.2 Backward Pass
e computer continues by making a backward pass (see Figure6.15). One
looks for the latest nish and latest start for each activity that is acceptable
if one should ...