266 • Practical Project Management for Building and Construction
• Planning of human resources and equipment needed to perform
the test
• Schedule for testing
• Checklists for testing
• Physical conditions for testing
• Description of test method, step by step
• Opening meeting
• Checking that the reference materials are in place
• Implementation
• Component control, control of quality and quantity (sometimes
called FAT 1)
• Control that the soware and the internal systems of the product
work (sometimes called FAT 2)
• System test: verifying that the system works together with exter-
nal systems through simulation of the external interface (some-
times called FAT 3)
• Verication of operational and maintenance requirements
(sometimes ...