111
6
Knowledge Areas
e text of this chapter is based on a hypothetical industrial facility with
oces, research and production facilities, and central media supply with
high standards of delivery performance. is can be used in the prepara-
tion of a project management plan. ose named as responsible are sug-
gestions—not requirements.
6.1 CONTACTS WITH AUTHORITIES
WHAT permits and approvals are needed?
HOW and WHEN can these permits be obtained?
e regulatory process is generally as shown in Figure6.1.
6.1.1 Permits for Building, Demolition,
Earthwork, and Temporary Measures
In order to protect citizens, third parties, and other interests rela