104 • Practical Project Management for Building and Construction
requirements. If not, the building will have a sloppy appearance. Choice
of color scheme is oen missing in inquiry documents. A color scheme
that is prepared aer the contract is awarded can result in unnecessary
discussion about additional economic compensation.
5.4.3 Detailed Design: Inquiry and Building
Documents for DC/TK Contracts
5.4.3.1 Inquiry Documents
• Purpose
• Ensure overall objectives, without limiting the possibility for the
DC/TK contractor to produce economic solutions.
In a TK/DC enquiry, the feasibility study and programming (see Section
5.3) are supplemented with geotechnical investigation, an outline overall
plan, a possible outline layout showing the requiremen ...