DRAWING A NETWORK WHEN ACTIVITIES REPRESENTED BY NODES ARE GIVEN
Problem 6.1
Draw the network for the following activities and find critical path and total duration of project.
Activity | Duration (Days) |
1-2 | 20 |
1-3 | 25 |
2-3 | 10 |
2-4 | 12 |
3-4 | 5 |
4-5 | 10 |
Solution
Various Paths | Duration of Paths |
1 - 2 - 4 - 5 | 20 + 12 + 10 = 42 |
1 - 2 - 3 - 4 - 5 | 20 + 10 + 5 + 10 = 45 |
1 - 3 - 4 - 5 | 25 + 5 + 10 = 40 |
Hence the critical path is 1 - 2 - 3 - 4 - 5 with project duration of 45 days.
Problem 6.2
Draw a network from the following activities and find critical path and duration of project.
Activity | Duration (Days) |
1-2 | 5 |
Get Quantitative Techniques: Theory and Problems now with the O’Reilly learning platform.
O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.