DRAWING A NETWORK WHEN ACTIVITIES REPRESENTED BY NODES ARE GIVEN

Problem 6.1

Draw the network for the following activities and find critical path and total duration of project.

 

Activity Duration (Days)
1-2 20
1-3 25
2-3 10
2-4 12
3-4 5
4-5 10

Solution

Critical Path and Total Duration of Project
Various Paths Duration of Paths
1 - 2 - 4 - 5 20 + 12 + 10 = 42
1 - 2 - 3 - 4 - 5 20 + 10 + 5 + 10 = 45
1 - 3 - 4 - 5 25 + 5 + 10 = 40

Hence the critical path is 1 - 2 - 3 - 4 - 5 with project duration of 45 days.

Problem 6.2

Draw a network from the following activities and find critical path and duration of project.

 

Activity Duration (Days)
1-2 5