USEFULNESS OF CPM
CPM plays an important role in project planning and control.
- Network indicates the specific activities required to complete a project.
- Network indicates the interdependence and sequence of specific activities.
- It indicates the start and finish time of each activity of the project.
- It indicates the critical path.
- It indicates the duration of critical path.
- It indicates those activities for which extra effort would not be beneficial in order to shorten the project duration.
- It indicates those activities for which extra effort would be beneficial in order to shorten the project duration.
- It enables the project manager to deploy resources from non-critical activities to critical activities without delaying the overall project duration. ...