CALCULATION OF EXPECTED DURATION AND VARIANCES OF ACTIVITIES
Problem 7.1
A project has the following activities and characteristics:

Required:
- Find expected duration of each activity
- Draw the project network and expected duration of the project
- Find variances of activities on critical path and its standard deviation
Solution
(a) Expected duration of each activity and their variances
Activity | Expected Duration ![]() |
Variance ![]() |
---|---|---|
1 - 2 | ||
1 - ... |