CALCULATION OF EARLIEST START TIME, LATEST FINISH TIME AND FLOATS

Problem 6.71

A project has the following activities:

 

Activity Duration (Days)
1-2 2
1-3 4
1-4 3
2-5 1
3-5 6
4-6 5
5-6 7

Required

  1. Draw the project network.
  2. Find the critical path and total project duration.
  3. Find earliest start time, latest start time, earliest finish time, and latest finish time.
  4. Find total float, head even slack, free float, tail even slack and independent float.

Solution

Part (a)

project network

Part (b)

Various Paths Duration of Paths
1 - 2 - 5 - 6 2 + 1 + 7 = 10
1 - 3 - 5 - 6 4 + 6 + 7 = 17
1 - 4 - 6 3 + 5 = 8

Hence the critical path ...

Get Quantitative Techniques: Theory and Problems now with the O’Reilly learning platform.

O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.