Problem 7.3
Tulsian Ltd., has undertaken a project which has an expected duration of 15 days with a variance of 9 days.
Calculate:
- The probability that the project will be completed on or before 12 days.
- The probability that the project will be completed on or before 18 days.
- The probability that the project will not be completed on or before 12 days.
- The probability that the project will not be completed on or before 18 days.
- The probability that the project will be completed in not less than 3 days earlier than expected.
- The probability that the project will be completed in not more than 3 days later than expected.
- The probability that the project will take more than 12 days, but not more than 18 days.
- The probability ...