DRAWING NETWORK WHEN ACTIVITIES (INCLUDING DUMMY ACTIVITIES) REPRESENTED BY NODES ARE GIVEN.
Problem 6.25
Draw a network from the following activities and find a critical path and duration of project.
Activity | Duration (Days) |
1-2 | 30 |
1-3 | 7 |
2-4 | 10 |
3-4 (Dummy one) | 0 |
3-10 | 30 |
4-5 | 14 |
4-8 | 21 |
5-6 | 10 |
6-7 | 7 |
7-8 (Dummy one) | 0 |
7-9 | 7 |
8-9 | 12 |
8-10 (Dummy one) | 0 |
9-11 | 15 |
10-11 | 15 |
Solution
Various Paths | Duration of Paths |
1 - 2 - 4 - 5 - 6 - 7 - 8 - 9 - 11 | (30 + 10 + 14 + 10 + 7 + 0 + 12 + 15) = 98 |
1 - 2 - 4 - 5 - 6 - 7 - 9 - 11 | (30 + 10 + 14 + 10 + 7 + 7 + 15) = 93 |
1 - 2 - 4 - 8 - 9 - 11 | (30 + 10 + 21 + 12 + ... |