[Ans: (a) Expected Duration: 5, 6, 7, 9, 8, 9, 7, Variances: 1, 0, 4, 1, 4, 1, 1, (b) Expected Duration of Project 21 Days, (c) Sum of Variances of Critical Activities, 10, Std. Deviation 3.16]
Calculate: