PRACTICAL QUESTIONS
- A project has the following activities and characteristics:
Required:
- Find expected duration of each activity and their variances.
- Draw the Project Network and expected duration of the project.
- Find variances of activities on critical path and its standard deviation.
[Ans: (a) Expected Duration: 5, 6, 7, 9, 8, 9, 7, Variances: 1, 0, 4, 1, 4, 1, 1, (b) Expected Duration of Project 21 Days, (c) Sum of Variances of Critical Activities, 10, Std. Deviation 3.16]
- Tulsian Ltd., has undertaken a project which has an expected duration of 15 days with a variance of 9 days.
Calculate:
- The probability that the project will be completed ...
Get Quantitative Techniques: Theory and Problems now with the O’Reilly learning platform.
O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.