Key Equations

(5-1)

MAD=|Forecast error|n

A measure of overall forecast error called mean absolute deviation.

(5-2)

MSE=(Error)2n

A measure of forecast accuracy called mean squared error.

(5-3)

MAPE=|ErrorActual|n100%

A measure of forecast accuracy called mean absolute percent error.

(5-4)

Moving average=Sum of demands in previous n periodsnforecast

An equation for computing a moving average forecast.

(5-5)

Ft+1=Yt+Yt1++Ytn+1n

A mathematical expression for a moving average forecast.

(5-6)

Ft+1=(Weight in period i)(Actual value in period i)(Weights)

An equation for computing a weighted moving average forecast.

(5-7)

Ft+1=w1Yt+w2Yt1++wnYtn+1w1+w2++wn

A mathematical expression for a weighted moving average forecast.