Network models such as PERT and CPM are used
to plan large and complex projects.
to schedule large and complex projects.
to monitor large and complex projects.
to control large and complex projects.
for all of the above.
The primary difference between PERT and CPM is that
PERT uses one time estimate.
CPM has three time estimates.
PERT has three time estimates.
with CPM, it is assumed that all ...