A time-consuming job or task that is a key subpart of the total project.
A network in which the activities are represented by arcs.
A network in which the activities are represented by nodes. This is the model illustrated in our book.
Three time estimates that are used in determining the expected completion time and variance for an activity in a PERT network.
A procedure that moves from the end of the network to the beginning of the network. It is used in determining the latest finish and latest start times.
A probability distribution that is often used in computing the expected activity completion times and variances ...