Solved Problem 9-1 Don Yale, president of Hardrock Concrete Company, has plants in three locations and is currently working on three major construction projects, located at different sites. The shipping cost per truckload of concrete, plant capacities, and project requirements are provided in the accompanying table.
Formulate Hardrock’s transportation problem as a linear program and solve using software.
| TO FROM | PROJECT A | PROJECT B | PROJECT C | PLANT CAPACITIES |
|---|---|---|---|---|
| PLANT 1 | $10 | $4 | $11 | 70 |
| PLANT 2 | $12 | $5 | $8 | 50 |
| PLANT 3 | 9 | $7 | $6 | 30 |
| PROJECT REQUIREMENTS | 40 | 50 | 60 | 150 |
Define the variables as
where