Solved Problems
Solved Problem 12-1 The Maitland Furniture store gets an average of 50 customers per shift. The manager of Maitland wants to calculate whether she should hire 1, 2, 3, or 4 salespeople. She has determined that average waiting times will be 7 minutes with 1 salesperson, 4 minutes with 2 salespeople, 3 minutes with 3 salespeople, and 2 minutes with 4 salespeople. She has estimated the cost per minute that customers wait at $1. The cost per salesperson per shift (including benefits) is $70.
How many salespeople should be hired?
Solution
The manager’s calculations are as follows:
NUMBER OF SALESPEOPLE 1 2 3 4 (a) Average number of customers per shift 50 50 50 50 (b) Average waiting time per customer (minutes) 7 4 3