In the previous Kanban section, we mentioned that one of the key aspects of Kanban is to control the amount of work that is sent through.
While a work constraint is a concept that's used in Kanban, sometimes people also adopt it with Scrum. This allows you to use Scrum for planning and Kanban for execution in a hybrid methodology called Scrumban.
To set up column constraints for your agile board, go through these steps:
- Browse to your project's agile board.
- Click on the Board menu and select the Configure option.
- Select the Columns option from the left navigation panel.
- Select how you want the constraint to be calculated in the Column Constraint option. By default, Kanban board will use the Issue Count option, ...