For both Scrum and Kanban, the board's columns are mapped to the workflow that's used by the project, and the default workflow that's created is very simple. For example, the default Scrum workflow contains three statuses—To Do, In Progress, and Done. However, this is often not enough, as projects will have additional steps in their development cycle, such as testing and review. To add new columns to your board, follow these steps: