• time frames and schedules: any changes to the overall schedule or
to key milestones within the schedule should be subject to project
board approval;
• exceeding or likelihood of exceeding project tolerances: in respect of
budget, schedule or quality, the tolerances stipulate the allowable
deviation before the project board must report to programme
management and, in the case of budget implications, those making
investment decisions (which will be discussed shortly). Movements in
the project‘s schedule may have broader implications for the
programme, while increases in the budget could raise affordability
issues. Decreases in the project budget should ...