What: |
Monitoring project costs and managing use of project resources. |
When: |
Project execution and control. |
Results: |
A record of project costs, with plan adjustments as required to meet budget expectations. |
Cost control is central to project plan execution. It follows status collection and plan-variance analysis in the project-tracking cycle. It is necessary in any cycle where you discover a significant cost or effort variance, or your earned-value management measurements are over the limit. For each variance use cause-and-effect analysis to review its root cause and impact on the project timeline. If the root cause relates to individual or ...