What: |
Determining that all defined project activities have an owner, and when needed, sufficient additional staff. |
When: |
Project planning. |
Results: |
A two-dimensional responsibility matrix summarizing coverage and responsibilities for project work. |
Review your activity definition and use it to define roles for project work using a RACI analysis:
• R: Responsible (Contributor)
• A: Accountable (Owns the work—one “A” per activity)
• C: Consulted (Approvers, decision-makers)
• I: Informed (Provided with information)
Examine the staffing for project activities using a two-dimensional responsibility-assignment matrix listing the defined project activities ...