TIME PROCESS85Schedule Development (PMBOK® 6.5, Develop Schedule)
What: |
Developing a project schedule based on calendar dates. |
When: |
Project planning, execution, and control. |
Results: |
Identification of critical paths and a schedule that can be used for analysis, negotiation, and tracking. |
Document Relevant Nonproject Dates and Factors
Schedule development is a central component of project plan development. It combines activity duration estimating with activity sequencing to determine calendar dates for the project, based on bottom-up analysis.
Begin the process by creating a project calendar. Identify all significant dates important to the project, including the project start date, any project constraints, interim and final deadlines, ...