| What: | Monitoring project costs and managing use of project resources. | |
| When: | Project execution. | |
| Results: | Accurate project expenditure tracking and plan adjustments as required to manage budget expectations. |
Cost control is central to project plan execution. It follows status collection and plan-variance analysis in the project-tracking cycle. If you are outsourcing work, cost control also involves procurement control. It is necessary in any cycle where you discover a significant cost or effort variance, or your earned-value management measurements are out of limit. For each variance, use cause-and-effect analysis to review its root cause and ...