| What: | Determining project activity dependencies. | |
| When: | Project planning. | |
| Results: | A graphical or tabular summary of project workflow. |
Activity sequencing is generally done in parallel with activity duration estimating and activity resource estimating during project plan development and in line with your schedule planning. Sequencing is a bottom-up workflow analysis process. It should never be based on arbitrarily imposed, top-down fixed deadlines. If any significant project-timing issues arise, plan to resolve them using constraint management and plan optimization and by negotiating project changes, not by imposing unrealistic calendar constraints.