Here are some of the problems with timeboxing.
Attempting to timebox unsuitable work products. I don't recommend using timeboxes for upstream activities (or beginning-of-the-food-chain activities) such as project planning, requirements analysis, or design—because work on those activities has large downstream implications. A $100 mistake in requirements analysis can cost as much as $20,000 to correct later (Boehm and Papaccio 1988). The software-project graveyard is filled with the bones of project managers who tried to shorten upstream activities and wound up delivering software late because small upstream defects produced large downstream costs. Time "saved" early in the project is usually a false economy. ...