Here are the keys to success in using timeboxing:
Use timeboxing only with projects that you can complete within the timebox time frame (usually from 60 to 120 days).
Be sure that end-users and management have agreed to a core feature set that the timebox construction team believes it can implement within the timebox time frame. Be sure that features have been prioritized, and that you can drop some of them from the product if needed to meet the schedule.
Be sure that the timebox team is signed up for the ambitious timebox project. Provide any motivational support needed.
Keep the quality of the software high throughout the timebox.
If you need to, cut features to make the timebox deadline. Don't extend ...