Appendix B (Chapter 4) ◾ 263
Today is 4/1/XX
Fill answers in the blanks: (Some answers provided in italicized parentheses)
A. Pick date changes and downward rescheduling subunit
1. Set hot key for supply/demand inquiry and hot key for manufacturing order inquiry.
2. View manufacturing orders M100 and chart the dates; also chart order M200.
M100 M200
Due Due
Start Start
Pick Pick
Cut
Cut
Firm Firm
3. Change the pick date of M100 to 4/10/XX.
Why? (is allows an extra four days for the pick/build cycle.)
What does the order status screen for order M100 advise for the new due date of component
Y? (ey have changed.)
Should components Z and D a