438 Appendix A
Discussion questions (Phase V)
Interpret the resulting parameters from Step 6 and answer the following:
a. What is the projected project cost?
b. What is the projected cost overrun?
c. What is the projected project duration?
d. How much of the project has been completed at this point?
e. The cost performance gures for each task are not impressive;
however, the overall difference in cost versus baseline values do not
seem so bad. What might be hiding this?
Review
Go back through the major steps and review results of each iteration. Note
the output goals for each of the following milestones:
a. Create the basic plan
b. Update the plan with actual durations
c. Reschedule the plan at a dened status date
d. Compute EV parameters ...