277Chapter fteen: Earned value management
have overrun by 20% do we anticipate the rest of the project to suddenly
start tting the baseline plan durations? Research says that projects tend
to develop a culture early in the cycle such that by this time the project has
established its normal behavior for the rest of the life cycle. Once this issue
is decided, it is time to either modify the rest of the plan accordingly or
assume that it will go as planned from this point forward. If the same trend
continues, one has to start dealing with how to forecast completion values.
In any case, the current project plan should represent the latest views ...