267Chapter fteen: Earned value management
directly from the Gantt bar status. Note that for the status point tasks A
and B planned to complete, the project PV would be $10 + $20 or $30. EV
calculation is a little trickier. The rule says that you can only earn what
you plan. Assuming the %Complete values are correct, EV would be $10
for task A and $10 for B (half of the plan value). So, the project EV would
be 20. We now have dened two of the three required parameters.
The last variable needed is actual cost. The question in your mind at this
point might be “where would one nd actual costs for the project?” Going
back to the material in Ch ...