218 Project management tools and techniques
having paint on the carpet, resulting in lower quality, rework, manage-
ment issues, and so on. In most cases, the original plan should have been
constructed with an optimal technical sequence, so fast tracking is chal-
lenging that sequence.
Before deciding to fast track a project, it is necessary to evaluate the
technical characteristics of the project. If it involves a new type initiative
or high interaction between the tasks, the risk level is further elevated.
If critical path time can be cut by overlapping, evaluate the value of that
decrease compared to the increased risk and management effort involved.
Recognize that there are many factors involved in the decision to fast track
such that no si ...