223Chapter twelve: Creating a viable project plan
QUESTIONS
Review questions
Use sample car project plan titled 12 Car Project Case Discussion from the
publisher website to answer the following questions:
1. If you were able to cut any task in the car project by 10%, which task
would you choose to cut?
2. Given historical project performance slippage do you feel that the
“green” buffer in task 71 is adequate to protect the project schedule?
3. Do you see anything wrong with the recurring tasks?
4. Generate the WBS for this plan and comment on the logic of the
structure.
5. Do you see an opportunity to fast track in this structure?
In-class questions
1. Describe the term tweaking as used in this chapter. What is the goal
of this activit ...