360 Project management tools and techniques
network, these values will either have to be manually extracted from the
critical path or sorted by total slack value to group the critical path tasks
into a single manageable group. In this latter form, the critical path group
could then be exported to Excel for further manipulation. Once the proj-
ect T(E) and critical path standard deviation (σ) have been identied, the
required “shape parameters” are dened to evaluate expected project
duration and a measure of dispersion (range).
The CLT assumption supports the notion that the resulting project
probability distribution is represented by a normal ...