184 Project management tools and techniques
Pool project example problem
The rst step for this example is to identify the resources available for
allocation. Figure 10.7 denes the resource pool data to be used. Using the
resource pool data from Figure 10.7, each task is loaded with its dened
resources. The results of this are shown in Figure 10.8 under the Resource
Names column.
The cost indicated for each activity is automatically calculated based
on resource rates and the activity duration estimate. As a sample calcula-
tion, line four shows two plumbers (200%) being allocated for the 4-day
install piping activity. Plumbers make $40/h and the ...