287Chapter fteen: Earned value management
The initial view of project data evolves from work package level esti-
mates developed in the planning phase. This is heavily oriented toward
the scope denition process related to the WBS and its companion diction-
ary data. In many ways, a formalized WBS Dictionary could inherit much
of the data storage role described here.
Basically, the structure of project data falls into two broad categories:
planning and execution/control. Planning data evolve from the processes
leading up to the approved baseline, while the latter subset deals with
actual performance status tracking of those work units. Much of the data
element denition links are achieved using the WBS ID as a common ref-
erence code. In some ...