344 Project management tools and techniques
Example 3: Manually moving tasks
In this example, the PM is faced with an overallocated mechanic for task
1.2.5.1, chassis. The total slack is 185 days and the duration for the task
is 20 days as displayed in Figure 19.19. Therefore, the best way to handle
this overallocation is to simply move the task to a different 20-day time
period that does not violate the range of the slack time period. This is
accomplished by manually moving the Gantt bar with the mouse to an
open time period. The start date was 11/4/2013 and nish date 11/29/2013
for the task. The task in the Gantt chart view was moved with the ...