339Chapter nineteen: Resource leveling
Example 1: Adding resources
In this example, the PM is faced with overallocated designers as dis-
played in the resource usage chart in Figure 19.11. Scrolling from right
to left, we quickly learn that the designer category currently has four
designers but needs two additional designers. The additional designers
are needed since there is a continuous overallocation issue through-
out the project. In this situation, the PM gets authorization from man-
agement to hire two additional designers, increasing the designer
resource category from four to six. Therefore, resources can be added
to MSPby clicking i