Variable time project planning
Introduction
Up to this point task durations have been shown as a single time estimate
and from that a project schedule and completion date were calculated.
Sufcient background has now been developed to relax this simplifying
assumption. It should now be obvious that project dynamics and the related
complexity will make any work unit estimate somewhat uncertain. For this
reason, it is time to explore how to handle this recognition. Think about
the implications of this new view. If the plan says that a project is going
to be completed on June 1, we now know that is highly unlikely to be the
case. ...