211Chapter eleven: Introduction to risk
signal activation of the event. The term trigger is used and can be dened
as an early warning sign that a risk has occurred or is about to occur. An
identied item in the risk register is a risk event and its corresponding trig-
ger (PMI 2008). A planned response to the risk can also be tracked in the
risk register along with the risk owner, responsible person for handling the
risk, and the probability and impact assessment. Last, the status column is
used to signal the status of the event through the life cycle.
Summary
Risk planning begins with a series of steps designed to help approach,
plan, and execute the risk management activities, which constitutes the
rst major step in risk management and w ...