137Chapter eight: Activity estimating
show allocations for each of these and they each represent an estimate in
their own right. Risk assessment is an estimating process designed to cre-
ate an appropriate reserve for this class of work, but the other two catego-
ries are left to dene as an experience-based estimate. In any case, time
and cost estimates for these three reserve-type costs groupings are addi-
tive to the overall project direct estimates. Each of these has the potential
to expand the initial planned time and cost of the project.
Overhead
Overhead occurs as a result of the project being supported by the mother
organization. The project staff is paid and supported by this organization.
In addition to the direct salaries shown as labor ...