262 Project management tools and techniques
planned and scheduled, the next step is to estimate the resource
requirements (budgets) for all the dened work units. Each dened
WBS element must have a resource value estimated for its specied
work. Management will then approve this in the form of an autho-
rized project budget. Individual WBS work units will not contain con-
tingencies or management reserves in the EV analysis portion. These two
reserves are held separately.
Step 4—Plan and schedule dened work. The EV methodology
requires a resource management system that is capable of tracking
authorized resources (budgets) through the approved schedule. The
comparison plan must reect a time-phased budget mapped to the
authorized schedule. From ...