292 Project management tools and techniques
12. Where can rate and use variance help?
13. Assuming that you have accurate raw data why might an EAC forecast
be wrong even if it is assumed that the project will continue as it has?
In-class questions
1. This simple Gantt chart plan contains three activities. PVs for each
activity are shown in bold font on each bar. Task completion esti-
mates are shown as a percentage and time period two is the status
point. The accounting system has collected actual costs for the three
activities as 6, 12, and 6, respectively. Compute the EV parameters for
this model. What is your prediction for cost and ti ...