132 Project management tools and techniques
standard phases planned for this effort and an estimated overall bud-
get of $2,500,000. Dened phases include: Initiation, Planning, Design,
Construction, and Deployment. The Construction phase is further decom-
posed into three subgroup activities—frame, exterior, and interior. Past
projects indicate the following resource breakdown across the phases:
Initiation = 10%
Planning = 15%
Design = 15%
Construction = 40%
Deployment = 20%
Activities within the Construction phase typically consume resources
in the ratio:
Frame = 14%
Exterior = 13%
Interior = 13%
Using these values, the Construction phase would receive 40% of the
estimated budget which would compute to $1,000,000 (i.e., 0.40 * $2,500,000).
Within t