392 Project management tools and techniques
sees what the effect on project completion would be if it took its optimistic
or pessimistic duration, while all other tasks took the deterministic value
(Barbecana, Inc. 2011b). Sensitivity analysis can be in the form of a tornado
diagram that ranks the project activities in order of signicance for, say,
critical path (Richardson 2010). The tornado diagram helps decide where to
focus attention. An example of a tornado diagram is shown in Figure 22.3.
Modeling and simulation is another form of quantitative risk analysis
(Richardson 2010). It is a typical method used to simulate project outcomes
by assign ...