232 Project management tools and techniques
not a formal risk assessment process performed during planning, some
budget reserve should be set up for this class of event based on history,
gut feel, or whatever technique the organization wishes. The movement
of funds from this reserve pool should also be under the approval control
of the project board much in the same fashion as a scope change. In many
ways, the risk event acts in much the same form as a change dictated by
some natural event—that is, weather, technology, and so on.
Management reserve
MR is dened as “. .. budgets reserved for unplanned changes to project
scope and cost” (PMI 2008, 177). This reserve category is dened to handle
“unknown/unknowns.” The most common examples of this ...